With all but 6 villas now accounted for, Northbrook will see the last of building and construction in May 2012. The available villas for purchase are 59, 60, 62, 81, 84 and 7. These are all single garage options in various locations within the village (refer to site plan) Completion of 81 and 84 will be mid September, villas 59, 60, and 62 prior to Christmas 2011 and villa 7 completed April 2012.
May 23rd 2011
Since our last update we have steadily confirmed sales for new residents at Northbrook Villas. The remaining villas in the complex that have internal access garage are the Blue plan (102m2) and the Grey plan (106m2). We also have 2 smaller 66m2 Red plan options currently under construction; these villas meet the needs of residents not requiring a garage.
March 2011
With the real estate market in Christchurch now in uncertain times, it has been pleasing to experience the consistent interest shown towards Northbrook villas over the past few months. Sales and demand have steadily increased accommodating many differing needs. Although the earthquake of 22nd Feb has introduced many new residents, the interest from people outside of Canterbury has seen our building team step up their development programme to complete all but the northern boundary villas and the south east corner villas. With the interest shown on our remaining villas, it is likely these will be snapped up before the cooler winter months arrive.
You owe it to yourself to visit
Viewing over weekends between 1 - 3pm on Saturday and Sunday - all welcome.
June 23 2010
In spite of the cold weather it has been business as usual at Northbrook Villas with continued interest and progress in completing Stage One of the village. With over 30 villas spoken for and 12 villas now occupied, the day to day feel is developing into a pleasant community. We have 4 villa’s completed and available for viewing with 3 villas available for immediate possession and many others available in the near future. Don’t miss out on securing your new home prior to pending GST increases on 1st October 2010.
May 2010
8 Villas are now occupied.
25 Sold or under offer.
3 Show Villas now available to view.
Clubhouse is now well under way with the frame up.
6 Villas have just commenced construction.
Very steady enquiry and interest.
Pending government GST rise to %15 and the cost of steel and timber will increase current prices in the near future. Secure your villa now.
April 2010
4 more villas now have residents living in them.
The landscaping is now taking shape with lawns well established around the completed villas and gardens are starting to grow.
Another unique water feature has been installed in front of Villa16.
MAR 2010
21 villas are now under offer or sold.
19 villas are either completed or under construction.
Building of the clubhouse has now commenced.
4 Completed show homes and others to view at various stages of completion..
FEB 2010
Stage one will have 32 villas completed over the coming months with 16 already sold / on hold and 18 either completed or under construction.
With this demand Jed & Mark (The developers) have re-worked the later stages of the complex to include a further 8 double garage options.
JAN 2010.
With the commencement of stage one now well underway, visitors can view 4 completed show homes and easily see how the village is taking shape.
Stage one will have 30 villas completed over the coming months with 8 already sold and 18 either completed or under construction. Our first resident Mrs Betty Brown moved in prior to Christmas and being an avid gardener is taking to the task of completing her gardens and landscaping.
Roading for stage one was completed in December with kerbing and parking defining access and villa boundaries.
The little extra's in this development really make a difference...
- Solar water heating is being acknowledged as a wonderful saving and feature
- The size and finish of the completed villas is being seen as a real advantage over other options in today's market.
- A new water feature at the entrance to the complex has had many positive comments.
- Double garage options are proving popular with 4 of the available 6 villas sold.